Site Evaluation
It is good practice to schedule a site evaluation with the general
contractor and architect/owner prior to commencement of any maple
flooring installation.
The site evaluation should take place no sooner than 30 days after the concrete
slab is poured. At this time you can inform the involved parties of your
on-site needs and requirements. Below are the things you should make
the general contractor and architect/owner aware of during a site evaluation
meeting:
- All roof work should be completed, including flashing,
guttering and exterior drainage.
- The building must be permanently enclosed and weather-tight.
- All block, brick, masonry, tile, marble and/or
terrazzo work must be complete, cured and dried.
- Concrete flatness and moisture content must meet
the requirements detailed in MFMA Position Statements "Concrete
Slab Moisture Content" and "Concrete Slab
Flatness."
- All interior painting must be completed and dry.
- The permanent light, heating, electrical and ventilation
systems must be operating.
- All overhead work must be complete, and the floor
area must be free of obstructions.
- All backstops and sports accessory fixtures must
be installed.
If you have additional questions, contact
MFMA's Technical Director at 847-480-9138.